According to the assistant representative of the Government in Alicante, Encarna Llinares, the new dual carriageway section of the N332 between Torrevieja and Pilar de la Horadada will be opened today. There is still plenty of work to complete but at least traffic flow will be eased during the summer with two lanes in each direction.
The work which had a budget of 24.332.898 Euros was scheduled to be completed within 32 months. At present 11 of the 12kms are completed. There are still road markings and traffic signals to install. The cycle track isn’t finished and the new roundabouts will need landscaping.